Registration of lease rights to the land selected by the customer, obtaining pre-authorizations and approvals, specifications Term of implementation of Phase III - 8 months
|
1. Preparation of a topographic survey and determination of the boundaries of the requested area. 2. Solving the basic questions in the administration controlling land, the allocation of land with the signing of letters of intent with the administration and the administration of the municipality that allows a site. Initiation of the preliminary order and agreement about the allocation of land. 3. Preparation of the Act of site selection and approval of all necessary permits, consents and monitoring bodies and institutions, with the order and any necessary preparation and other expert opinions and projects (in particular in the bodies of Sanitary Inspection, Fire Protection, Historical and Cultural Heritage Foundation of geological information, Office of the Ministry of Nature Protection, Department of architecture and Construction, communications center and district electrical networks, forestry, land management and the Committee on land Resources and other agencies) 4. Preparation of technical specifications for connection to all the required communications with provision of necessary facilities (electricity, gas, communications). Obtaining a license to extract water from the water well. 5. Obtaining a license to quarry for sand and deposit it in the area. 6. The question of removal of foreign communications networks evolved from the area to give them ownership of all of the necessary technical specifications and other documentation 7. Transferring of the site from the category of agricultural land to the category of industrial land, and other special purposes (order and conduct research on the characteristics of the soil cover to the provision of the necessary receipt of documents on the history of land use, education committee, with the activation of the results of its operations to determine the size of the loss of agricultural production .) Based on the documents, initiation of the decision of this issue in the administration of the Federation and the Governor for obtaining the order for the transfer of land. 8. The order and carrying out a land surveying of a site, with removal of borders in nature, completion of all necessary legal and land survey documentation, with its transfer to the land committee for registration in the Single State Register of Lands (EGRZ), statement on cadastral accounting. Based on thel collected set of documents initiation of the final Resolution on provision in lease of the parcel of land, preparation and the organization of agreement signature of lease. 9. Registration of a lease in the Department of Justice for state registration for the rights to real estate and transactions with it.
|
V |
Construction Management - Term of realization of Phase V: Implementation design work - 6 months; - Depositing sand in the area - 20 months; - Construction - 18 months.
|
6. Selection of a contractor from among the organizations involved in geodetic and geological surveys. Conducting expert risk assessments, including advice on their evaluation with the department of non-departmental examination, Department of Industry Development Administration of the Novosibirsk region, as well as in construction and design organizations. Signing a contract with the selected organization offering the most favorable terms. 7. Selection of a contractor from among the organizations involved in the design. Conducting expert risk assessments, including advice on their evaluation in the department of non-departmental examination, Department of Industry Development Administration of Novosibirsk region, as well as in construction and design organizations, checking logistics on-site, business (including financial) reputation, the availability of experience of industrial design. Signing a contract with the selected organization offering the most favorable terms. 8.Selection of a contractor to develop a career and land reclamation sand. Conducting expert risk assessments, including advice on their evaluation in the department of non-departmental examination, Department of Industry Development Administration of Novosibirsk region, in the construction and design organizations, checking logistics on-site, business (including financial) reputation, review completed and ongoing objects. Signing a contract with the selected organization offering the most favorable terms. The height of the sand deposit 3 to 4 meters. Volume of about 1 million cubic meters 9. Selecting a general contractor, organizations, material suppliers and construction contractors for various types of construction work. Conducting expert risk assessments, including advice on their evaluation in the department of non-departmental examination, Department of Industry Development Administration of Novosibirsk region, in the construction and design organizations, checking logistics on-site, business (including financial) the reputation, experience of industrial construction , viewing the construction and completed projects. Signing a contract with the selected organization offering the most favorable terms. 10. Maintenance work surveying, design, construction and other contractors on the contracts, including:
- monitoring performance of the contract for the duration of the contract;
- Monitoring the current status of work, predicting possible difficulties;
- Addressing operational issues;
- settlement of disputes, including administrative and supervisory bodies;
- control of funding, with the right to stop, resume, and complete cessation of payments, imposing of sanctions, control of settlement with the subcontract organizations to maintain the pace of work.
11. Obtaining permits and approvals for the connection of communications: electricity, water lines, gas, and contracts for their design and construction. 12. Organization and direct involvement in the conduct of labor and the state commissions, supervision and complete support in putting it into operation. The State Commission on commissioning the object was carried out in two days, now object is maintained by the owner.
|